| Date: |
Construction Activity: |
| May 2 |
Wall framing and prep trusses |
| May 3 |
Install trusses; install sub fascia; install rafter ties; start decking |
| May 7 |
Roof decking; soffit vents; exterior insulation |
| May 10 |
Windows; begin vinyl siding |
| May 14 |
Vinyl siding |
| May 17 |
Vinyl siding |
| May 21 |
Insulation |
| May 24 |
NO WORK - Memorial Day |
| May 28 |
Dirt work; grade for yard |
| May 31 |
Paint |
| June 4 |
Install trim; install interior doors |
| June 7--updated construction schedule |
clean out inside of house; prep for paint; finish vinyl siding |
| June 11 |
prep forms for concrete; pre-paint trim; paint |
| June 14 |
paint; start installing trim; prep floors for vinyl |
June 18
June 21
June 25
June 29 |
trim out house
hardware installation; seed & straw yard
Clean house
4:30 p.m. Dedication Ceremony! |